Speaker Aryal Lays Foundation Stone for Budhigandaki Hydropower Project Office

Speaker Aryal Lays Foundation Stone for Budhigandaki Hydropower Project Office

Gorkha, Nov 25: Speaker Dol Prasad Aryal laid the foundation stone for the office building, residential building, and concrete bridge of Budhigandaki Hydropower Company Limited on Wednesday.

The foundation stones were laid for the construction of buildings at Siurenitar in Gorkha Rural Municipality-8 and for a concrete bridge over the Budhigandaki River connecting Siurenitar in Gorkha and Kalleri in Dhading.

The foundation stone-laying ceremony was attended by Minister for Physical Infrastructure Sunil Lamsal, former Prime Minister Baburam Bhattarai, Member of Parliament for Dhading-1 Ashika Tamang and local stakeholders.

The company stated that the total cost of constructing the office building, residential building and bridge for the Budhigandaki Hydropower Project is Rs 372.85.

MS Bisht Sindhuli JV has been awarded the construction contract for the buildings. The agreement between the contractor and Budhigandaki Hydropower Company Limited was signed on Asoj 31.

The company stated that construction of the office building, residential building and bridge is expected to be completed by Jestha 17, 2085.

With the foundation stone laid, construction preparations for the 1,200 MW reservoir-based Budhigandaki Hydropower Project, a national pride project, have formally begun.

According to company Chief Executive Officer Arun Rajouria, modern infrastructure, including the project’s administrative office, staff residential facilities and entrance gate, will be constructed within the camp area.

He said construction of the camp had begun to accommodate the administrative and technical personnel required at the project site before work starts on the main dam and powerhouse.